Bangladesh has begun drawing electricity from nuclear power for the first time. The first unit of the Rooppur Nuclear Power Plant started a trial supply of 350MW to the national grid at 3:16pm on Tuesday, 17 November, in the presence of Science and Technology Minister Faqir Mahbub Anam.
The initial connection is planned to last eight to ten hours. Engineers will use the window to monitor how the turbine, generator and synchronisation systems behave once linked to the grid. The unit will then be disconnected for further tests and reconnected after roughly 28 hours for another four to six hours of checks.
Officials stressed that the connection is one stage in a gradual testing programme and does not mean the plant has entered commercial operation. Over the coming months the reactor, turbine, generator and automated control systems will be assessed, and the unit may be shut down temporarily at different stages.
Electricity produced during the testing period will still reach consumers. Regulatory approval and a trial operation of about ten months are expected before the unit is declared commercially operational.
Source: The Business Standard · Source date: 2026-11-17.
Report compiled by the SANn Asia desk from the linked source.